Cottage Grove proposes every‑other‑year neighborhood pulverization in draft 2027–2036 street plan
Summary
Staff presented a 10‑year street maintenance and pulverization plan proposing neighborhood‑scale reconstruction on an every‑other‑year cadence, using DOT PACER ratings to prioritize work and pursuing state LREP grants to reduce local cost.
Get email alerts on the Street Maintenance topic
No spam. Unsubscribe anytime.
Public works staff presented a draft 2027–2036 street maintenance (pulverization) plan to the committee on June 10, 2026, describing how DOT PACER pavement ratings and budget constraints shaped a neighborhood‑by‑neighborhood approach. The plan groups streets so that reconstruction can occur in single construction seasons rather than spanning multiple years for the same neighborhood.
Staff said the proposed cadence is every other year for major pulverization and reconstruction projects; off years are devoted to preventive maintenance such as crack fill and chip seal to extend pavement life. The approach seeks to balance the capital budget across a 10‑year horizon and to reduce multi‑year disruption for residents. Staff noted that PACER ratings vary block‑by‑block and that updates to PACER ratings will be done in 2027 to refine the schedule.
Committee members requested additional data, including the total miles of road represented in each scheduled project and clarified how PACER ratings translate into a decision to maintain or fully reconstruct a street. Staff committed to provide mileage totals and said they will re‑run ratings next year and adjust the plan as needed.
Staff also reported securing $47,000 in LREP funding toward a 2028 project and said they will continue to pursue state grants to offset local costs. The plan aims to concentrate work in neighborhoods developed in the same phases so sections with similar pavement lifespans can be addressed together.
Next steps: staff will supply requested mileage figures, re‑evaluate PACER ratings in 2027, refine the 10‑year schedule and present updates to the village board and public as part of the capital prioritization process.