Pinehurst residents demand immediate priority on repeated flooding; engineer cites blockages, promises plan
Summary
Pinehurst residents told the River Ridge CDD board they face repeated, dangerous flooding and demanded the district make remedies a top priority; District Engineer Charlie Krebs said inspections found debris and possible 25%+ blockages and will have inlets cleaned and provide a written remediation plan and timeline.
Get email alerts on the Pinehurst Flooding topic
No spam. Unsubscribe anytime.
Resident Mike Dugan urged the River Ridge Community Development District to make Pinehurst flooding its top priority, telling the board at its June 25 meeting that repeated flooding has crossed a “red line.” Dugan read a prepared statement saying residents are “galvanized” and may pursue legal options if the district does not commit resources and provide constant updates.
Another Pinehurst resident, Ed Nowak, read a prepared statement sharply criticizing the system redesign and calling it “flawed and unacceptable.” Nowak said that after recent storms Pinehurst streets remained flooded for days while other neighborhoods were dry and asked why receiver water levels in Pinehurst sit above outlet heights.
District Engineer Charlie Krebs said he inspected Pinehurst after videos were sent by Eric Long and found debris on grates and in pipes; MRI inspected the next day, removed leaves from a grate and flushed debris from pipes. Krebs told the board that some drains in Pinehurst may have more than 25% blockage and recommended cleaning the inlets. He said crews flushed debris that was “not very compacted or solid” and planned further cleanings.
Board Chair Bob Schultz asked Krebs to prepare a written plan that details how the situation will be resolved and an estimated timeline and to provide it to the board, Eric Long and the Pinehurst NVR. Krebs agreed and confirmed MRI will clean the inlets.
Why it matters: Pinehurst residents described safety and access concerns after the June 12–14 storm and demanded rapid, prioritized action. The engineer’s findings point to routine maintenance and targeted cleanings as near-term steps, while the board signaled it will seek a formal remediation plan and timeline.
What’s next: Krebs will provide the written plan and timeline to the board and stakeholders; further funding or construction steps were discussed elsewhere on the agenda.