Platte County road crew details Fish Creek repair plan, proposes higher sign fees and moves to clarify North County Line Road status
Summary
Road and Bridge staff recommended a full double chip-seal for Fish Creek to repair deteriorated edges, proposed raising single road-name sign installation fees from $150 to $225, and directed staff to coordinate a survey and resolution with a neighboring county to clarify North County Line Road ownership and access.
Get email alerts on the Roads And Infrastructure topic
No spam. Unsubscribe anytime.
Road and Bridge staff told the Platte County commission they plan to rebuild damaged Fish Creek shoulders with millings and apply a double chip-seal across the full 8.1-mile route to restore the road base and prevent recurring edge failures. The presenter said local millings are available and using the adjacent Alexander Construction pit would reduce hauling time.
The presenter summarized cost drivers and near-term price changes for chip-seal materials: suppliers reported chip-oil increases of about $15 per ton and tentative short-term pricing holds if the county commits quantities. Staff estimated a per-mile chip-seal cost rising from prior-year averages (personnel discussed all-in estimates approaching about $410 per mile for a larger program) and cautioned the board that doing eight miles this year (versus the typical six) would require drawing more from scarf funds.
On fees, staff proposed raising the fee for installing a single road-name sign from $150 to $225 (and a double sign from $225 to $270), noting the county currently loses money on installations. Commissioners agreed staff should update the county website and fee schedule to reflect the change.
Commissioners also spent significant time on North County Line Road, which the county has maintained under a long-standing maintenance agreement with the adjacent county but has not been formally declared a county road. Staff reported three homes currently use the route for legal access and that multiple parcels could be involved. The board directed staff to contact the neighboring county (to ask about splitting survey costs), engage Benchmark (engineers) to prepare survey exhibits, and begin outreach to affected landowners so a resolution to initiate formal proceedings could be prepared for a future meeting cycle. If adjacent landowners agree to sign rights-of-way, the streamlined declaration process could avoid a viewer appointment and public hearing; if not, the formal petition process would be required.
The board discussed the implications for pending land-use variances (noting turbine setbacks can be measured from county roads) and agreed to keep the road on the variance list while pursuing survey and resolution work. No final decision to reclassify the road was recorded; staff were instructed to start the survey and return with a proposed resolution and cost-sharing plan.