Cridersville reports new water booster pump, meter installs and plans to address Village Café leak
Summary
Council heard that the village installed a new booster pump and valves at the water plant, has been adding meters at unmetered facilities per Ohio EPA requests, and that administrators are exploring enforcement steps related to a water leak at the Village Café.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Village officials told the Cridersville council on Feb. 10, 2025, that the water system has received equipment upgrades and that staff will pursue enforcement steps related to an ongoing water leak.
At the Committee of the Whole report, Joe Bailey said the village received a new water booster pump and valves for the water plant that were installed by Global Electric. "We received our new water booster pump and valves," Bailey stated. Village crews and Dotson's Plumbing and Heating have installed water meters in several facilities that previously lacked them to meet an Ohio EPA request to track all water usage.
Village Administrator Jarid Kohlrieser and Solicitor James Hearn are evaluating options the village can use to enforce or manage the water leak issue at the Village Café; Bailey said the village anticipates being able to start taking some action within the next few weeks. Council Member Steve Numbers also said the administrator continues to explore options to acquire land for a potential new water well project.
The minutes do not specify the technical cause of the Village Café leak, the party responsible, or the enforcement tools under consideration; council indicated follow-up action will be forthcoming in subsequent meetings.