Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Solar Project topic
No spam. Unsubscribe anytime.
Solar installation proceeding at Greene County middle school; battery slab installed on campus
Summary
District staff reported that ballast systems for rooftop solar are being installed at the middle school, that a battery slab has been poured and that the project sequencing will be middle school, then high school, then elementary with expected completion by August.
Get email alerts on the Solar Project topic
No spam. Unsubscribe anytime.
District staff updated the board on the ongoing solar installation: ballast systems were being installed on the middle school roof, a concrete slab for an on-site battery has been poured, and the installation plan is to complete the middle school first, then the high school and finally the elementary (roof-mounted at the elementary). When asked for a timeline, staff said the project is expected to be finished in August.
Administrators noted a city setback request that required adjusting the array layout (the city asked that panels be 50 feet off Grimmel), and said the battery will be sited just off the southwest corner of the elementary building. Board members had no substantive questions beyond timeline clarification.

