Board approves Live Oak Electrics generator work to be paid from building fund
Summary
After reviewing two quotes for a building generator, the board approved proceeding with Live Oak Electrics; the job will be charged to the building maintenance fund rather than the capital fund, per staff advice.
Get email alerts on the Infrastructure Generator topic
No spam. Unsubscribe anytime.
The fire chief reviewed generator quotes for the Live Oak site and said one bidder provided a more itemized quote while the amounts were comparable. Staff explained the unit is sized to run all three breaker panels in the building and that interior wiring will be required to connect the panels.
A board member moved to proceed with Live Oak Electrics and specified the expenditure would come from the building maintenance fund rather than the capital fund. The motion was seconded and carried by voice vote.
Board members discussed that using the building fund would be appropriate and that the work should be able to be completed in a matter of weeks; one member noted the city can avoid a rental fee by using in-house equipment for installation.