School District No. Re-2 Brush board approves phase-one secondary campus site plan, sets May 18, 2025 graduation

School District No. Re-2 Brush Board of Education · November 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a Phase One site plan for the secondary campus (opting for a 1.0× 100-year pond size), directed an RFQ process for an owner’s representative, and voted to move the 2025 graduation to May 18. Personnel and a final-reading policy were also approved by roll call.

The School District No. Re-2 Brush Board of Education approved a Phase One site plan for the district’s secondary campus and voted to move the 2025 graduation date to May 18 during its regular meeting.

Board action: At the meeting the board voted—by roll call—to adopt the Phase One site plan with the smaller stormwater option (1.0 times the 100-year event) after staff said the district’s existing ponds had held an unusually large storm earlier this year. The board also approved a motion to change the 2025 graduation date to May 18, citing the need to wait for community-college grades to be returned before commencement.

Why it matters: Approving the Phase One site plan clears a key procedural step for campus development and for advancing design and permitting. Picking the 1.0× pond profile affects the size, excavation and likely cost of the campus detention pond; board members discussed a larger 1.5× alternative but settled on the smaller option as consistent with existing campus capacity. Moving graduation affects schedule and notification for seniors and families and resolves a scheduling conflict tied to external grade reporting.

Details and process: Superintendent (reporting under the superintendent’s report) said the district will post a request for qualifications (RFQ) for an owner’s representative (construction manager) on its website; the timeline in the board packet sets a site-visit date of Dec. 3, questions due Dec. 5, responses by Dec. 10, shortlisted interviews on Dec. 16 and a public notice of selection on Dec. 17. The board noted a potential special meeting on Dec. 16 to take action if it wishes to select the owner’s representative at that time.

Traffic and stormwater trade-offs: Trustees discussed traffic congestion at arrival/dismissal and the possible extension of a third lane on Be Digger Drive to reduce queuing. The site plan includes an option to extend the lane; however, board members emphasized that final timelines and paving decisions are budget-dependent. During discussion a staff member reported that Chad Cox described an earlier heavy rain as a “thousand-year” storm and said existing ponds had held that event; the board cited that observation in arguing the smaller pond would be adequate for Phase One.

Other actions at the meeting: The board approved the personnel report and adopted policy BG on final reading. The consent agenda was approved earlier in the meeting by roll call.

What’s next: Staff will post the RFQ and accept questions through Dec. 5; if the board proceeds with interviews Dec. 16 it may need a special meeting to act on a selection. The approved Phase One site plan will be forwarded for city review and to the district’s project contacts for next procurement and design steps.