Versailles administrator reports on utility incidents, equipment plans and facility upgrades

Versailles Village Council · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Administrator Francis reported on recent utility outages attributed to on-site equipment damage and over-height machinery, a $29,686 replacement recloser option with a 35-week lead time, completion of Well #9 rehab ($21,450), a $9,182.88 dugout grant, an Oct. 16 McGreevey Rd. substation bid opening, and other public-works updates.

Village Administrator Francis delivered an operations-focused report covering utilities, public-works projects and community events.

He said personnel from the AMP Thermostat Program will present at the Oct. 22 council meeting about a demand-response program to help the municipal electric utility and customers reduce load during peak events. Francis also reported that a NKTelco franchise fee (5% of gross revenue) for customers inside the village limits has taken effect under Ohio Revised Code provisions; those receipts will be deposited into the Village General Fund.

Francis summarized recent electric outages: on Sept. 27 an east/southeast outage began just before 2 p.m. when a dump truck bed struck an overhead telecom line, causing conductor spans to slap together and lock out a circuit recloser; power was restored at about 2:26 p.m. Walls Bros. will be invoiced for time and expenses related to that event. A separate outage on Oct. 3 affected customers south of the village; crews found two destroyed fuse cut-outs and restored power by 4:38 a.m.; staff said an over-height farming implement likely struck overhead lines.

On equipment, Francis said the Greenlawn Substation recloser was damaged on Sept. 22; a new Cooper recloser is available for $29,686 with a 35-week lead time. The village is pursuing a temporary unit through Power Line Supply and exploring rebuilding an existing damaged recloser as a nearer-term option.

Water and wastewater updates included completion of the WWTP digestor drawdown for winter storage; operators have adjusted chemical dosing to address a change in finished-water softness caused by the Reed Rd. wellfield; and Well #9 was rehabilitated by Jackson Well Services for $21,450 and is back in service.

Francis also reported smaller capital and maintenance activities: LED lighting upgrades at Ward Park; demolition and pad work for new Indian Creek Park dugouts supported by a $9,182.88 grant and additional Park Fund expenditures; new metal street light bases poured along Klipstine Road; sale of a 2009 bucket truck for $16,200 on GovDeals; and a McGreevey Rd. Substation major equipment bid opening scheduled for Oct. 16 at 2 p.m.

Fiscal Officer Alisha Apple told council the budgeting process will begin shortly.