Village of Mamaroneck outlines river maintenance, drainage projects and permit timeline
Summary
Village staff reported ongoing river surveys and maintenance, drainage improvements on Florence and Wood streets, and permit work expected by December; DPW stressed debris removal and sediment management after Hurricane Ida.
Get email alerts on the Flood Mitigation topic
No spam. Unsubscribe anytime.
Village of Mamaroneck officials on Sept. 23 updated the Board of Trustees on flood-mitigation and drainage projects, saying surveys and permitting work are advancing and several local repairs are on track.
The meeting’s presiding officer asked the village manager and engineer to brief trustees on recent work. The village engineer (Speaker 5) said Spinelli is nearly finished surveying Columbus Park, the river confluence, Rockland Avenue and the area behind Reinecke High School. Those survey results will go to the village’s consultant to begin permit applications, and staff said they expect the permits to be in place by December.
Staff flagged three near-term projects. Florence Street drainage improvements are proceeding on time and on budget, with anticipated completion before Nov. 1. Work on Wood Street and Jefferson Avenue requires relocation of four utility poles along Wood Street’s south curb to accommodate a proposed box culvert and storm drain; that relocation depends on a schedule from Consolidated Edison, staff said. The village is preparing contracts and specifications so work can be put out to bid once the Con Edison schedule is confirmed.
Public works staff (Speaker 6) described routine river maintenance since Hurricane Ida: removing branches, vegetation, fallen rocks and other debris that create snag points; maintaining machine access for dredging; flushing low-lying storm lines; and clearing outfalls where heavy flows can cause restrictions. The DPW emphasized that accumulated sediment and lodged debris reduce culvert and river capacity and that crews are working to reduce downstream build-up.
Board members asked staff to keep the trustees informed of permit timelines and Con Edison coordination so bidding and construction can proceed without further delay. The mayor asked staff to update the board as soon as they have the Con Edison schedule.