Summary

At its Oct. 21 meeting the Tremont Select Board awarded the Seal Cove Road construction contract to BFP Trucking and Rings Paving for $53,502 from the Road Improvement Reserve and authorized a temporary paving repair for culverts on Kelleytown Road; both motions passed unanimously.

The Tremont Select Board on Oct. 21 awarded the Seal Cove Road construction contract to BFP Trucking and Rings Paving for $53,502, to be paid from the town’s Road Improvement Reserve. The motion, made by Select Board member Kevin Buck and seconded by Howard Goodwin, passed unanimously.

At the same meeting the board authorized a temporary repair for culverts at the marsh on Kelleytown Road, approving a motion by Eric Eaton, seconded by Kevin Buck, to pave over the existing culvert area as an interim fix. That motion also passed unanimously.

The board approved FY25 warrants #35–#41 during the meeting, listing the following amounts: #35 $14,833.23; #36 $69,000.00; #37 $14,871.83; #38 $132,650.83; #39 $15,029.36; #40 $1,503,894.37; and #41 $222,453.04. The warrants were approved on a motion by Kevin Buck, seconded by Eric Eaton, and the vote was unanimous.

The board also accepted the town’s July–September 2024 financial reports on a motion by Kevin Buck, seconded by Howard Goodwin; that motion passed unanimously.

These items were handled as part of regular business; no public comment or debate about the contracts, repairs, or warrant amounts is recorded in the transcript. The board placed related infrastructure items—specifically a Seal Cove ramp repair and safety building discussion—on the agenda for the next meeting for additional consideration.