Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Paving topic

No spam. Unsubscribe anytime.

Council approves paving and striping contract using remaining ODOT earmark

Orville City Council · September 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a contract to mark and pave a DARPM project with a low bid just under $400,000; city staff said the work will be funded through leftover ODOT earmarked funds and requires ODOT approval before construction begins.

The Orville City Council on Sept. 16 approved Resolution 28-24 authorizing the safety service director to enter into a contract for paving and markings on a DARPM project. City staff said two bids were received and the low bidder came in at just under $400,000.

The speaker explained this work will be paid from remaining ODOT-allocated earmarked funds originally set aside as part of an earlier federal earmark project; because the funds are ODOT money, city staff said the contract and project must be routed through ODOT's approval process before construction can start. "We did have 2 bids submitted... The low bidder was... They did come in at just under, $400,000. And, again, this project is being completely funded through ODOT money," a staff member said.

A councilmember asked whether the money is one-time; staff replied the remaining earmark is what is being used and once spent it will not be replenished. Council suspended the three-day reading requirement and passed the resolution.

Next steps: staff will submit the bids and recommended award to ODOT for its review and approval and will return to council with any required documentation and timelines.