Summary

City staff reported a phased wastewater repair plan with an initial $600,000 estimate to replace filters and stabilise the reuse line, and urged administrative and legislative help after delays with the finance authority and state environmental review.

City of Portales officials outlined a phased plan to repair and optimize the municipal wastewater system, estimating an initial round of work at roughly $600,000 to repair filters and bring key screens and sensors online before larger pipeline work proceeds.

The city’s presentation said engineers identified parts of the treatment process operating "backwards" from design, sending water inefficiently through a holding pond instead of routing it first to the reuse line. The city manager said replacing manual procedures with sensor-driven screens and automation would reduce repeated pump failures — pumps described in discussion as costing about $26,000 each — and make the plant more reliable.

Why it matters: Officials said completing an initial repair before extensive pipeline relocation will make later work less costly and reduce recurring maintenance. City Manager testimony emphasized that the fixes would allow reclaimed water to be put to nonpotable uses and reduce demand on potable supplies.

Board members and staff discussed temporary options while permanent work proceeds — including reopening a bypass line and trucking or pumping flows back to the plant for reprocessing — and the need to clean any reopened lines before returning them to service. "We have to finish a loop that goes back to that pond by design," the City Manager said, describing the reuse-loop requirement.

Funding and administrative hurdles featured prominently. Staff described repeated questions from the finance authority and the New Mexico environmental office that can add weeks and costs. Officials said the engineering firm quoted four to seven weeks and thousands of dollars to produce a technical memorandum requested by funders; examples given during discussion included figures in the $7,000–$17,000 range. The City Manager asked the board for administrative support such as formal letters to state agencies or legislative contacts to help clear approvals more quickly.

The board did not vote on project funding during the meeting; members asked staff to provide an outline of the technical information and letters needed so the board can supply coordinated documentation to funders and regulators. The meeting record shows the board approved the prior meeting minutes earlier in the session and set follow-up tasks for staff to refine project costs and financing options.

Next steps: Staff will determine whether the $600,000 stage can be covered from available funds or whether the project must be packaged for the finance authority and the Water Trust Board, then return with a clarified scope, timeline and a draft letter the board can use when contacting outside agencies.