Beach and recreation director seeks $70,000 to resurface Johnny Kelly courts

Capitol Outlay Committee · October 23, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Beach and Recreation Director Dustin Pino asked the Capitol Outlay Committee for $70,000 to resurface four tennis courts and three basketball courts at Johnny Kelly Park, arguing resurfacing now will extend life by 8–10 years and avoid a larger $400,000 reconstruction later.

Dustin Pino, the town’s Beach and Recreation Director, asked the Capitol Outlay Committee on Oct. 23 for $70,000 to resurface the courts at Johnny Kelly Park, saying resurfacing now would extend usable life by another 8–10 years and prevent more costly reconstruction.

Pino said the request covers resurfacing the plexi‑pave top layer used on tennis, pickleball and basketball courts and includes contingency and prevailing‑wage pricing. "So the $70,000 I'm asking for will take care of all the surfaces, including contingencies," he said, adding that resurfacing is preferable to deferring repairs and risking a full rebuild that could approach $400,000.

Committee members sought unit‑cost context. Pino described court inventory as four standard tennis courts (approximately 120 by 80 feet each) and three high‑school sized basketball courts (about 90 by 50 feet), which he estimated totals roughly 52,000 square feet of playing surface. Using his figures, a staff member calculated a ballpark unit cost of about $0.80 per square foot; Pino said his estimate accounts for prevailing wage and mobilization costs.

Members discussed phasing versus doing all courts at once. Pino recommended resurfacing a single location in a single mobilization because the specialized surfacing contractor is limited in New England and mobilization costs make staged projects materially more expensive. He also said resurfacing would address crown and drainage issues that can lead to cracking, and that resurfacing closures would likely take less than a week.

A resident who uses Johnny Kelly Park urged the committee to approve maintenance, stressing year‑round heavy use for leagues, camps and tournaments. Pino noted the courts are central to summer camp programming (about 150 children daily) and year‑round public use.

Next steps: The committee asked for the usual backup on square footage and unit pricing to be added to the updated funding sheets; no formal vote was taken Oct. 23.