Florence approves water-main and sewer pay requests, and contract change order for Eagle Post Road project
Summary
The board approved vendor work and pay requests for Eagle Post Road overlay and the Hwy. 49 sanitary sewer additions project, including a $60,116.03 pay request to A.J. Construction and a $131,230.53 pay request to Thornton Construction plus a $60,298.67 contract change order.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Florence's city engineers and board members approved multiple construction pay requests and a contract change order tied to the Eagle Post Road and Hwy. 49 sanitary sewer projects during the Oct. 7 meeting.
City Engineer Tim Parker recommended Pay Request No. 2 to A.J. Construction for $60,116.03 for the Eagle Post Road overlay LPA project. Alderman Grantham moved the approval, Alderman Herrin seconded, and the motion carried unanimously.
Parker also recommended approval of Pay Request No. 1 to Thornton Construction Company, Inc. for $131,230.53 related to MCWI #255-2-CW (Hwy. 49 Eagle Post Road sanitary sewer additions — College Street pump station force main replacement). The board approved that pay request after a motion by Alderman Grantham and a second by Alderman Sistrunk.
The board further approved Thornton Construction Company, Inc. Contract Change Order No. 1 in the amount of $60,298.67 for the Phase 3 sanitary sewer additions project. That change order was approved on a motion from Alderman Sistrunk and a second from Alderman Martin.
Notable procedure: Alderman Mason Herrin briefly left the meeting after the A.J. Construction pay request; the record notes he did not participate in deliberations or votes taken while absent and was later invited back to resume participation.
What’s next: The approved pay requests and change order authorize payment to contractors per the project contracts; the meeting record does not disclose additional funding sources or revised project completion dates.