City engineer: Highland–Trebisky water-main rehab delayed by defective pipe; sewer and road projects to start this spring

City of Richmond Heights City Council · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Engineer Justin Haselton told the council that half the pipe delivered for the Highland–Trebisky water-main rehabilitation was defective and returned for recoating, causing a reported 1–2 week delay plus weather-related time lost; sanitary-sewer work near Belle Oaks is slated to start mid-March and Edgewood Road design will be bid this spring.

City Engineer Justin Haselton updated Richmond Heights City Council on Feb. 10 about three infrastructure projects, reporting a delivery problem on the Highland–Trebisky water-main rehabilitation that will delay work and giving timelines for sewer and road projects.

On the CWD Highland–Trebisky Transmission Main Renewal Phase 2, Haselton said the project involves rehabilitating a 48-inch concrete water main to a 42-inch steel main along Trebisky Road from Highland Road to Monticello Boulevard, with an anticipated completion in June 2026. "The contractor discovered the pipe that was delivered was defective - (1/2 of the project). The pipe had to be sent back to be re-coated and tested. This will set them back 1-2 weeks. They have also lost a week due to weather. There has been no official completion date extension yet," he said.

Haselton also reported that a kickoff meeting was held for the NEORSD sanitary sewer improvements project near Belle Oaks and surrounding neighborhoods and that construction is tentatively scheduled to begin in mid-March, with recent coordination meetings between the contractor and Belle Oaks representatives. On Edgewood Road, the field survey is complete and the design is in progress; the project is expected to be bid in the spring and constructed in summer/fall.

Haselton identified Fabrizi Trucking & Paving Co., Inc. as the contractor for the water-main renewal and said the recently discovered pipe defect affected roughly half the project's delivered materials. Council did not vote on project funding or contract changes during the meeting; Haselton said there has been no official change to the completion date.