Vinalhaven commission considers $120,000 SCADA system, plans town meeting to authorize borrowing
Summary
Commissioners reviewed a proposed $120,000 SCADA system for the wastewater treatment plant, decided DEP rules require a single-phase installation, and asked the town manager to explore borrowing options rather than raising rates; a Town Meeting will be needed to authorize debt.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Town of Vinalhaven Sewer Commissioners on Jan. 27 discussed installing a new SCADA (supervisory control and data acquisition) system at the island wastewater treatment plant and the financing required to pay for it.
John Hughes of Maine Water summarized operations and the broader need for the upgrade; the commission recorded an estimate of $120,000 for the new SCADA system, described in the minutes as roughly one‑fourth of the current total sewer budget. Commissioners noted the system could improve remote monitoring and control, but members were not in favor of funding it through a direct rate increase.
Town Manager Marjorie Stratton told the commission she would contact local banks to compare borrowing rates and consult bond counsel about issuing debt. Minutes record that state Department of Environmental Protection (DEP) requirements mean the project must be completed in a single phase rather than in two stages, which affects timing and financing needs.
Because borrowing will be required, the commission recorded that a Town Meeting will be necessary to authorize the debt. The minutes also note the Water District needs Town approval for a separate Debt Service Assumption Agreement; staff suggested the two items could be considered at the same Town Meeting.
Next steps recorded in the minutes: Stratton will solicit loan options and bond counsel advice; the commission did not adopt a financing plan during the meeting and explicitly rejected increasing sewer rates at that time. The minutes did not include a formal motion with a vote tally on the SCADA purchase or on a borrowing plan.