Thayne council approves larger change order after clay found under Community Center lot

Thayne Town Council · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council accepted Sunrise Engineering's recommendation to remove unsuitable clay under the Community Center south parking lot and approved a change order to import additional pit‑run and excavation up to 1,300 cubic yards above the original bid.

Thayne — The Town Council on April 21 approved a change order to address unsuitable clay discovered beneath the Community Center's south parking lot.

Sunrise Engineering representative Robert Hood told the council crews removed sidewalks and old pavement and found clay that would compromise the new surface. He offered two options: fully remove the clay and refill with pit‑run (estimated about $40,000), or roughen the material, let it dry and later fill with pit‑run (estimated about $9,000). After discussion the council chose the more robust full‑removal option to avoid future failures.

Council approved a motion to add pit‑run at $21 per cubic yard and additional excavation and haul at $8.35 per cubic yard, authorizing up to 1,300 cubic yards above the original contract amount. Councilman Heward moved the change order and Councilwoman Passey seconded; the motion carried.

Sunrise also noted additional concrete removal in front of the building estimated at 400 square yards at $9 per square yard ($3,600). The firm will continue oversight of related TAP and Van Noy Street exploratory work to check for similar subsurface conditions along planned paving corridors.

The council did not provide a revised total contract figure in the meeting and left the final accounting to forthcoming change‑order paperwork and contractor documentation.