Goshen board approves change order for Lincoln–Story reconstruction after testing finds low‑strength soils

Board of Public Works and Safety and Storm Water · June 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Change Order No. 8 for the Lincoln Avenue at Story Avenue reconstruction after engineering staff reported on-site testing found low‑strength soils as deep as about 2 feet; staff recommended undercutting and installing multiaxial geogrid with aggregate to stabilize the roadway subgrade.

Engineering staff told the Board of Public Works and Safety that on‑site DCP testing at the Lincoln Avenue and Story Avenue intersection revealed areas of low‑strength soils as thick as 2 feet, and recommended undercutting and installing multiaxial geogrid with aggregate to stabilize the subgrade.

Staff said after reviewing alternatives with Tensar personnel they determined undercutting and placement of two layers of multiaxial geogrid (NX750) with aggregate between the layers “would provide the most economical means of adequately stabilizing the subgrade.” Staff presented estimated plan sheets and unit pricing, including a listed block excavating price of $7.76 per square yard for the NX750 geogrid.

The board moved to approve Change Order No. 8 (job number 2019 00046). The motion as read in the meeting record said the change order amount is $37,55 in the transcript; staff stated the change, combined with previous changes, increases the contract value by 3.67%. The motion was seconded and passed unanimously.

Staff noted the change order does not include common excavation costs that would have been necessary regardless of the undercutting method and that no additional consultant fees were requested to complete the work. The board did not request additional information before approving the change order.