District reports completed roofing work, gym floor replacement timeline and operations ticket metrics

San Felipe-Del Rio CISD Board of Trustees · June 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

San Felipe‑Del Rio CISD reported the high school roofing project is complete, San Felipe Memorial Middle School gym floor demolition and underlayment are finished with contractors returning for finishing work next week, and shared maintenance, technology and transportation ticket closure rates for the prior 90 days.

District facilities and operations staff updated the board on construction and work‑order performance at the June 15 meeting.

Mr. Chapa said the high school roofing project (all five wings) is complete, and the San Felipe Memorial Middle School gym floor demolition and underlayment installation are done; contractors will return next Monday to complete nailing, sanding and painting, with full completion expected by mid‑July. The district has also replaced the athletic turf field.

Operations metrics for the previous 90 days showed 1,084 maintenance tickets received with 797 closed (74% overall); closure rates varied by age bucket (0–15 days 54%, 16–30 days 74%, 31–60 days 74%, 61–90 days 81%). The technology department received 2,848 tickets with 2,473 closed (87% overall) and reported 60% closure in the 0–15 day bucket and higher closure rates in other buckets. Transportation received 203 tickets and closed 186 (92%). Board members had no further questions after the report.

The board received the facilities and operations updates and will monitor completion of construction work ahead of fall orientation.