Union City approves $22,295 repair for sinkhole, will replace 24-inch clay tile
Summary
Council approved a $22,295 contract with Mansfield to replace a 24-inch clay tile, reconnect pipes and install a larger catch basin at Municipal Lot #1 after engineering recommendations and two contractor bids were presented.
Get email alerts on the Infrastructure Repairs topic
No spam. Unsubscribe anytime.
Union City Borough Council voted Aug. 13 to hire Mansfield to repair a sinkhole at Municipal Lot #1, approving a $22,295 contract to replace a 24-inch clay tile, reconnect pipes, install a larger catch basin and replace approximately 10 feet of pipe.
Streets Supervisor Bob Phillips reported that a 68-foot section toward the Municipal Authority pipe bottom had failed and that the manhole in the other direction remained covered. Insight consultant Bob Carpenter recommended lining the pipes in sections; borough engineer Tim Wells also offered suggestions. The recommendation presented to council was to replace the 24-inch clay tile in the sinkhole area, reconnect all pipes there to the 24-inch line, replace the adjacent catch basin with a larger unit and replace about 10 feet of pipe.
Two estimates were on the table: Mansfield at $22,295 and McLallen Construction at $23,450. Both proposals required the borough to provide a truck during the work. Councilor Steadman moved and Councilor Osborn seconded the motion to award the work to Mansfield; the motion carried unanimously.
Council did not at the meeting specify a start date; Streets Supervisor Bob Phillips and the contractor will coordinate scheduling and the borough must provide a truck during construction.