Vinalhaven Board allocates $11,740 from Harbor Reserve to match DOT grant for downtown ramp parking work
Summary
The Board of Selectmen voted 5-0 on March 10 to appropriate $11,740 from the Harbor Reserve to provide the local match for a DOT grant for the downtown boat-ramp parking lot as ramp reconstruction begins; work will be phased so one ramp remains open and schedule will vary with tides.
Get email alerts on the Harbor Infrastructure topic
No spam. Unsubscribe anytime.
On March 10, 2026, the Vinalhaven Board of Selectmen voted 5-0 to appropriate $11,740 from the town’s Harbor Reserve to supplement matching funds for a Department of Transportation grant for the downtown boat-ramp parking lot. The appropriation came as reconstruction of both downtown boat ramps was reported to begin this week.
Gabe McPhail told the board she had pursued a DOT grant to help pay for the parking-lot portion of the downtown project and that, when finalizing the application, staff identified the need for an additional $11,740 from the Harbor Reserve as the local match. Pam Alley moved to appropriate the amount; the motion was seconded by Leslie Dyer and carried unanimously.
Town staff said both ramps will be rebuilt in sections so at least one ramp remains available for launching during construction and that the contractor’s schedule will depend on tidal conditions. The board’s appropriation covers only the local match for the parking portion of the project; overall project funding and schedules were not further specified at the meeting.
The appropriation is recorded as coming from the Harbor Reserve and will be applied to the grant match when the DOT application is finalized. The Selectmen did not specify a timeline beyond the contractor’s phased work plan and tidal constraints.