CCRPC approves preferred‑site letters for three proposed solar net‑metering projects
Summary
The CCRPC reviewed advance notices and approved three letters supporting preferred‑site designation for proposed solar net‑metering facilities in Colchester and Milton, contingent on avoiding or mitigating identified environmental constraints.
Get email alerts on the Energy Solar topic
No spam. Unsubscribe anytime.
The Chittenden County Regional Planning Commission’s Executive Committee approved letters supporting preferred‑site designation for three proposed solar net‑metering projects during its June 1 meeting.
Regina Mahony presented the advance notices and staff reviews. For 0 Mercier Drive in Colchester (advance notice #22‑0458‑AN) staff concluded the project aligns with the 2018 ECOS Plan and that steep slopes identified by the town would be avoided; the committee approved a letter to Aegis Renewable Energy endorsing the site as preferred. For two Milton projects — a 150 kW array at 413 Hibbard Road (#22‑1834‑AN) and a 146 kW array at 321 Bear Trap Road (#22‑1674‑AN) — CCRPC staff likewise found consistency with the ECOS Plan but flagged potential constraints including rare, threatened or endangered species, river corridors, and agricultural/hydric soils (and, for Bear Trap Road, high‑priority forest blocks). In each case, the commission’s support was conditioned on avoiding or mitigating identified constraints.
John Zicconi moved and Chris Shaw seconded motions to approve the letters and 45‑day notices as presented; each motion carried unanimously. The minutes note CCRPC may submit additional comments as the project filings progress and will re‑review site locations with subsequent submittals.
The committee did not record detailed vote tallies beyond "motion carried unanimously."