Summary
Committee members reviewed remaining terminal punch-list items including a disconnected heating zone affecting an ice‑melt system, missing interior keys, a hot computer room with no air exchange, and old gate posts that must be removed before June.
Get email alerts on the Terminal Projects topic
No spam. Unsubscribe anytime.
The Airport Advisory Committee reviewed outstanding punch-list items for the new terminal at its Jan. 6 meeting, identifying a number of maintenance and completion tasks that remain undone.
The committee noted a missing window screen, an unfinished center beam in the main room, and problems with the ice‑melt system. Shane McDougall said a heating zone appears to be disconnected; the disconnected pipes are likely the reason the ice‑melt system is nonfunctional. The committee also reported not having keys for several "break‑bar" interior doors and lacking keys other than for the flight planning room, which may require hiring a locksmith.
Members described building issues that had persisted since the previous summer: a kitchen stove whose clock keeps resetting and a computer room with no air exchange that becomes extremely warm. Committee members assigned removal of old gate posts to Pete Lehman and a contractor contact (Steve T.), noting the removal needs to occur before June but was delayed by equipment malfunction.
The committee discussed these items as part of routine project oversight; no formal vote or new budget allocation was made during the meeting. Committee members said Travis will check outstanding punch-list items later in the week.