Superintendent Dr. O'Neal told the finance committee the district eliminated about 40 positions over two years and can avoid major special‑education restructuring with roughly $400,000 more; the committee also reviewed a proposed $11.4 million full roof replacement at Norton Middle School with 55.63% MSBA reimbursement.
Get email alerts on the School Budget topic
No spam. Unsubscribe anytime.
Dr. O'Neal told the Norton Finance Committee that the district cut 11 positions in FY24 and 29 in FY25 — about 40 positions in two years — and has restored only a handful of those jobs.
"We were able to bring back about three" at fall town meeting, she said, and the district has identified about $1.2 million in reductions that would remove roughly 8–10 staff positions. She said an additional $400,000 would prevent changes to the middle‑school special‑education model.
Why it matters: Dr. O'Neal said the district's current structure at Norton Middle School assigns one inclusion special educator per team; losing staff would shift to one special educator per grade and make the district rely more on paraprofessionals and contracted service providers. She warned that without the additional funds the district would need to redesign how services are delivered to students on IEPs.
The superintendent described possible program adjustments and tradeoffs: "We can reduce elementary sections without much impact, but to avoid touching the special‑education model would cost another $400,000," she said. Committee members asked about the durability of that flexibility, and Dr. O'Neal said it depends on enrollment trends and state aid timing.
Roof proposal and timeline: The committee also heard a schematic‑level plan for a full Norton Middle School roof replacement with an initial budget estimate of $11.4 million. The district said the project team (design firm Tai and Bond; owner’s project manager Next Level OPM) is at roughly 25–30% design and that the Massachusetts School Building Authority (MSBA) would reimburse the town about 55.63% of eligible costs.
The town and district described how early estimates typically decline when the project is bid: "Bids often come in around 70–80% of the original estimate," the presenter said, and the MSBA reimbursement means the town would not bear the full $11.4 million. The district showed a planning scenario in which a 20‑year borrowing term would translate to roughly $65 per year on the average home; officials said that number depends on final bids and financing term.
Design choices and tradeoffs: Committee members asked about metal roofing versus asphalt shingles (the district said metal is about $1 million more) and about required code upgrades, insulation, and flashing work. Officials said those components and standard contingencies — including asbestos allowances required by MSBA process — are included in the estimate.
What happens next: The district and town said they expect to complete higher‑level design and advance to bidding if town meeting approves the project; presenters cited a target to bid in late 2026 with construction in summer 2027. The Finance Committee asked for continued updates and for the town to circulate updated budget and capital materials ahead of follow‑up meetings.
Ending: The committee did not vote on the school appropriation at this meeting; members set additional hearings and asked the manager and district to return with clarified numbers and options.