Dover Ave bridge replacement, spring paving set in Marquette County’s 2025 plan

Marquette County Traffic Safety Committee · April 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county scheduled a bridge replacement on Dover Ave over the Mecan River for June–August 2025 with a full closure; final paving is planned in spring for CTH D/Causeway and repaving for CTH J east of STH 22, with CTH A and CTH Z conditional on funding.

Marquette County highway officials told the Traffic Safety Committee on Jan. 8 that the county’s 2025 construction program includes a bridge replacement on Dover Ave in the Town of Crystal Lake. The project is scheduled to begin in June and finish in August; Dover Ave will be closed for the duration of the work.

County staff said final paving for CTH D/Causeway is planned for spring, and CTH J east of STH 22 to the county line will be repaved. Additional projects — CTH A south of CTH M and CTH Z — will proceed only if funding becomes available.

Committee members noted scheduling and funding remain contingent on available resources and standard construction-season timelines. No public hearing or formal vote tied to the projects was recorded in the minutes.