Pittsfield council awards sewer and water contracts, approves $140,000 loan revision
Summary
The council accepted bids from Sergeant Corporation for Main Street sewer ($968,985) and Library Street water main ($689,425), approved a $140,000 loan revision for the sewer project, and discussed financing and rate impacts; votes were taken by voice for each resolution.
Get email alerts on the Water And Sewer Projects topic
No spam. Unsubscribe anytime.
At its Sept. 16 meeting, the Pittsfield Town Council approved multiple procurement and financing measures to address sewer and water infrastructure needs.
The council accepted Sergeant Corporation's low bid of $968,985 for the Main Street sewer improvement (Resolution 2594). Department staff reported that this bid fits within the engineer's estimate though the town will supplement construction funding with a combination of loan and grant financing; staff requested authorization to seek an additional $140,000 low‑interest loan if necessary. The council approved the resolution by voice vote.
The council also accepted Sergeant Corporation's $689,425 bid for Library Street water main replacement (Resolution 2595). Staff noted that the Library Street funding is restricted to drinking‑water uses and that any unused funds must be returned to the grantor; the council approved that resolution by voice vote as well.
To cover the Main Street sewer shortfall, the council approved a loan revision (Resolution 2596) to borrow an additional $140,000 from a state SRF program at an interest rate staff described as approximately 2–2.5 percent; the resolution passed by voice vote.
Department staff advised the council that construction scheduling and specific work (for example, targeted trench lining or cross‑country elements) would be coordinated with the contractor following award. Council members asked about timing, inspector assignments and potential impacts on sewer and water rates. Staff said construction payments will not be due until after construction and that staff will return with estimates of future rate impacts to inform residents ahead of any rate changes.
The votes on these contract awards and loan actions were recorded by voice as approved; the meeting transcript recorded the roll calls as 'I' with no named roll‑call tally in the minutes.