The board was told state water-quality staff want Jefferson to replace a flushing filtration system with a non-flushing cartridge model; state funding up to $30,000 was mentioned and staff will meet engineers to evaluate cost and alternatives.
Get email alerts on the Facilities Infrastructure topic
No spam. Unsubscribe anytime.
Facilities staff told the June 9 committee that a state retest had been performed at the wrong sampling point (before the filters) and that post-filter readings were 0%, but regulators do not favor filtration systems that periodically purge and flush wastewater near the septic system. The state indicated it can provide up to $30,000 toward a replacement system, and the facilities director said the district will consult engineers and water-quality specialists to determine options and true costs.
Staff cautioned that filtration systems vary widely in cost depending on pass-level requirements and contaminant targets; transcript discussion placed likely replacement near the $30,000 range but noted some systems can cost substantially more. The facilities director said he will report back in several weeks with estimates and to confirm whether the state funding fully covers replacement.
Separately, the facilities report covered a failed building management controller that was replaced from a rebuilt spare and a plan to rebuild the removed controller for future redundancy. The custodial contract set to expire July 1 will be replaced with in-house hires, staff said, and the board approved purchasing six cafeteria tables from the facilities line using available funds.
The board asked staff to continue vetting filtration options and to return with engineering recommendations and a clear estimate of total costs and funding sources before any contract is awarded.