Summary
The Select Board reviewed an RFP draft and a $14,500 Sebago Tech proposal for site surveying and bidding documents, discussed fabric vs. steel vs. conventional buildings, and heard that municipal bond timing may push borrowing to fall; staff will bring Sebago Tech's proposal back for review.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Select Board members on Feb. 24 discussed next steps for replacing or improving the town's salt-and-sand storage building, including design options and financing.
Staff reported an RFP draft that would seek design-build bids with three options: a fabric structure, a pre‑fabricated steel building, or a conventional wood building. A Sebago Tech proposal listed $14,500 for an existing‑conditions survey, GPS elevations and site work needed to produce bid documents. Several board members said they wanted more information about the scope of the $14,500 line item before authorizing the expense and suggested discussing options with the Budget Committee.
On financing, staff said the main municipal bond bank's spring application window had recently closed, which would likely delay borrowing to the fall. An alternative lender (referred to in the meeting as "Northeast Bank") indicated it could offer municipal financing with flexibility to repay early, though possibly at higher rates. The board directed staff to place Sebago Tech's proposal on the next meeting agenda for further review and to continue working with potential lenders on timing and terms.
Next step: Sebago Tech's proposal will be reviewed at the next meeting; staff will continue outreach to bonding sources and return cost/budget scenarios for board and Budget Committee consideration.