Officials give timeline update for CAST animal-services bond project; completion targeted April 27, 2027
Summary
Mike Wheeler told the council that the $3.9 million CAST bond program has pivoted through several site options, construction will start Dec. 15, and the projected maximum build completion date is April 27, 2027; staff outlined remaining infrastructure items and noted vehicle purchases and program-office work.
Get email alerts on the Cast Bond Project topic
No spam. Unsubscribe anytime.
Mike Wheeler presented an update on the Cabot Animal Services bond program (CAST) during the Dec. 1 meeting, summarizing past project versions, current site work and a projected completion schedule.
Wheeler said the citizen-approved $3.9 million bond originally funded an earlier project ("CAST 1.0") but higher-than-expected costs forced the city to pivot through alternate sites ("CAST 2.0") and currently to a new site adjacent to a college property ("CAST 3.0"). He said city crews have completed earthwork, pad work and sewer infrastructure at the current site; a pre-construction meeting was held and dozers are scheduled to begin Dec. 15. Wheeler said the build is planned as a 14-month project with an allowance for winter delays and a maximum completion date of April 27, 2027.
Wheeler also listed expenditures already made or planned under the program, including architecture and engineering fees, demolition and retrofit work at a program office in a former Sears building, and three vehicles purchased under a prior resolution. He said roughly $879,000 in land proceeds was earmarked to supplement the bond to put the program back near the originally authorized total and that $2.9 million is budgeted for furniture, fixtures and equipment and startup costs for veterinary services.
Council members asked about the bridge and power-line work tied to site access; Wheeler said the bridge was projected to be completed in August 2026 and that power-line reroutes had been negotiated and would cost less than earlier estimates. Wheeler offered to provide photos, further schedule details and an opening date in follow-up communications.
Why this matters: The update explains how the citizen-approved bond is being used, shows the city’s plan to proceed with construction, and identifies schedule and budget items residents and stakeholders may monitor as the project moves to construction.