Board approves 2026 directional‑boring contract to improve reliability in Highview Meadows
Summary
The board approved staff's recommendation to award the 2026 directional‑boring bid to replace aging underground cable, prioritizing a two‑phase East Division project to reduce outages in Highview Meadows and Royal Oaks; seven bids were received, with the low bid in the low $700,000s and the high around $1.8 million.
Get email alerts on the Electric Infrastructure topic
No spam. Unsubscribe anytime.
The Utility Advisory Board voted to approve staff's recommendation to award the 2026 directional‑boring contract for underground electric work. Wayne, the presenting staff member, outlined a multi‑year program to replace aging 1970s–1980s underground cable, extend city fiber and conduit for future SCADA connections, and convert overhead lines to underground where warranted. "This is a 2‑year project. So, this year will be phase one of that," Wayne said, and he singled out the East Division/Highview Meadows work as the year's top priority to improve reliability.
Staff said seven contractors bid on the work; bids ranged from the low $700,000s up to about $1.8 million, while the CIP budget anticipated mid‑$1.5 million. Board members asked about cable lifespans (staff said 30–50 years depending on manufacturer), project scope in specific neighborhoods and a minor arithmetic error in a bid worksheet (staff acknowledged an input mistake but confirmed the total bid figure was correct). A motion to approve the resolution was moved, seconded and approved by voice vote.