A joint working committee reviewed budget scenarios and a draft interlocal agreement to create a shared public-works department. Presenters showed the towns currently spend about $1.8 million combined; committee members flagged a possible $355,000 first-year increase under one in-house model and asked for more analysis before select-board presentations.

A working committee meeting of officials and staff from Newcastle and a neighboring town examined a draft interlocal agreement and three budget models for a shared public-works department, concluding that while long-term savings are possible the first year could raise costs under several scenarios.

Presenters walked the group through a spreadsheet of operating, capital, debt-service and facility costs and said the two towns’ current combined contracted services total about $1.8 million a year. The committee reviewed three service-level models — a “premium” approach that mirrors current dedicated downtown crews, a lower-cost “standard” approach with a single crew, and a phased option that would start by taking on downtown contracts first — and described different financing assumptions for new and used equipment (five‑year vs. three‑year amortizations).

Committee members pressed the presenters on how cost shares would be allocated. One proposed formula would split equipment and facility costs by road‑mile share (roughly a 36/64 split in the model) while splitting admin and personnel 50/50; applying the mileage-based split in the presented spreadsheet reduced one town’s bill by roughly $45,000 while increasing Newcastle’s by about $401,000 under the standard, first‑year scenario. Presenters said applying grant funding to facility costs or staging purchases could materially accelerate the point at which the projects show cumulative savings.

Not everyone was persuaded the long-term savings were likely. An attendee, Rachel, summarized a common critique: “I get really tired of hearing those kind of pie in the sky numbers,” she said, urging the committee to ground projections in local operational realities. Other members emphasized variability in assumptions — historical contract inflation used in the model was described as about an 8% annual increase in contracted services over the prior 20 years, and presenters said they modeled a range of CPI and wage‑growth assumptions to test sensitivity.

Technical details discussed included assumed useful lives for vehicles and heavy equipment (examples in the presentation: pickup trucks ~8 years, heavier trucks 10–12 years), maintenance escalation (presenter used a roughly 5% maintenance increase in the model), and whether an in‑house mechanic would be included under premium service. Committee members also asked whether some services currently performed under separate contracts (sanitation, playground maintenance) could shift to the new department if the crews were available.

The draft interlocal agreement examined by the committee would create a three‑member oversight board responsible for policy and a managing town that would oversee employees. Legal review has been requested and the draft retains different withdrawal conditions depending on whether towns have incurred facility or debt obligations; committee members flagged the draft’s proposed 25‑year term as a substantial commitment and asked for clearer pre‑debt withdrawal language.

The committee agreed the next step is a formal, public presentation to both select boards and broader outreach before placing any warrant articles before voters. Members discussed timing constraints (warrant materials need to be finalized in mid‑April to appear on typical annual-warrant schedules) and noted an initial joint presentation was being targeted in the weeks ahead. The presenters said the spreadsheet and supporting budget tabs are available for review and that they will prepare a public-facing presentation that addresses the comments heard at the meeting.

No formal vote or binding decision was taken at the meeting; the committee asked staff to refine assumptions, pursue attorney review of the draft interlocal agreement, and schedule a joint select-board meeting for further public review.