Costa Mesa approves Fairview Road/Belfast Avenue traffic signal to improve crossings and access
Summary
The council approved a new traffic signal at Fairview Road and Belfast Avenue (CIP 26‑03) with crosswalk, bulb‑out and turn‑lane work; the $751,943 project is funded with gas tax and OCTA Measure M2 fair‑share funds and is expected to finish in spring 2027.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The council voted to approve construction of a traffic signal at Fairview Road and Belfast Avenue, a project staff said will provide a high‑visibility crosswalk, a bulb‑out to shorten pedestrian crossing distance, a northbound left‑turn pocket extension and intersection lighting. Public works staff noted the challenge of coordinating the new signal with closely spaced existing signals on Fairview and presented a signal‑timing simulation to demonstrate coordination.
Funding and timeline: The low responsive bid was $683,584; with a 10% contingency staff estimated the total project cost at $751,943. Funding sources are gas‑tax and OCTA Measure M2 fair share; staff said a city CIP contribution covers the remaining gap. Staff estimated construction completion in spring 2027.
Public response and council debate: Neighbors were split—some residents, including parents of teenage drivers and long‑time residents, said the intersection is hazardous and asked for the signal; others opposed adding a signal at that location and preferred traffic calming or corridor improvements. Council voted 5–2 to approve the project; Council Members Reynolds and Maher voted no and asked staff to accelerate corridor‑level multimodal work in the area.