Summary

City staff told council that bids for the wastewater lift station came in lower than expected, dropping the project from an initial $2.1 million estimate to about $1.2 million; Cheshire Contracting has executed documents and the city plans to close CIB funding on June 25.

City staff reported progress on Milford’s wastewater lift station on June 16, saying construction bids returned substantially below earlier estimates and the city will lower its loan and grant requests.

Staff said initial planning estimated the project at $2.1 million; final bids reduced that figure to approximately $1.2 million. As a result, staff said the city will reduce both the loan and the grant request by roughly $400,000 each, which will lower the city’s repayment burden. Cheshire Contracting has executed all documents and the city expects to close on CIB funding on June 25.

The city explained the funding mechanics: the loan is used up front and the grant is applied after construction; lower bids will preserve the 50/50 grant split originally anticipated. Staff said construction can begin as soon as CIB closes and estimated the work on the lift station should be finished within a few months rather than years.

Next steps: Close CIB funding on the scheduled date, finalize contractor mobilization and monitor construction milestones; staff will update council on timing and any change orders as work begins.