Wiscasset planning board advances North Point Brownfields cleanup plan, schedules site walk and public hearing
Summary
The Wiscasset Planning Board found Sevee & Maher Engineers’ North Point Fill Area Brownfields cleanup and shoreline stabilization application complete, accepted waiver requests unanimously, set a site walk for April 17 and scheduled a public hearing for April 27.
Get email alerts on the Brownfields Cleanup topic
No spam. Unsubscribe anytime.
The Wiscasset Planning Board on April 13 found an application for a Brownfields cleanup and shoreline stabilization project at the North Point Fill Area complete and accepted requested waivers, clearing the way for a site walk and a public hearing. Al Cohen moved the completeness finding and the waiver approvals, and both motions carried in unanimous 7-0-0 votes.
Jeffrey Read, representing Sevee & Maher Engineers, presented the application for cleanup of the town-owned North Point Fill Area on North Point Road, an approximately 4.5-acre parcel bounded by the Sheepscot River and adjacent to the Mason Station Power Plant. Read said the site was historically used as a dump for Mason Station waste and that buried and partially buried materials, including asbestos-containing material, remain along the shoreline. He said the project would include construction of a cover system over identified impacted soils and embankment stabilization in areas that have not previously been stabilized. The application notes that part of the shoreline lies within FEMA Flood Insurance Zone AE.
The board voted 7-0-0 to find the application complete and 7-0-0 to accept the waiver requests. The board designated three members—Al Cohen, Tony Gatti and Deb Pooler—to attend a site walk scheduled for Friday, April 17, 2026, at 4 p.m., and set a public hearing on the application for Monday, April 27, 2026. The transcript does not record substantive public comment or a formal decision on the project beyond those procedural steps.
At the meeting’s start, Chairman Karl Olson called the session to order at 7:00 p.m. and the board approved the minutes of March 23, 2026. The motion to accept the minutes passed 5-0-2, with Chairman Olson and Deb Pooler recorded as abstaining. The meeting adjourned at 7:38 p.m. on a 7-0-0 vote.
Next steps: the site walk on April 17 and the April 27 public hearing will provide opportunities for board members and the public to inspect the area and comment before the board takes any final action on the cleanup and shoreline stabilization proposal.