City of Kelso outlines phased plan for Tallywain Corridor; design money and timeline discussed

Board Council Commission Agencies · June 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City of Kelso representative Craig said a consultant contract is in place and phase 1 segment analysis (about $50,000) is underway; permitting and funding work are expected to take the project toward a construction readiness milestone around 2029, with construction lasting roughly one to two years.

Craig, representing the City of Kelso, updated the board on the Tallywain Corridor project and the consultant engagement. He said the city executed a grant agreement, completed a consultant selection through an RFP (Parametrix), and negotiated a scope that splits the work into phases and segments so parts of the project can be advanced independently. Phase 1 is a segment analysis, budgeted roughly at $50,000, to define environmental processes, limits, refined cost estimates and potential funding sources for the roadway, bridge and intersection segments. Craig said Parametrix is ‘off and running’ on the phase‑1 contract.

Craig described the phasing logic: bridge alignment often dictates roadway alignment; alignment through airport property requires coordination with airport authorities and may force certain segments to be combined into a single delivery package. He said the team expects permitting and design work to push schedule outcomes such that construction readiness is likely in the 2029 timeframe, and he estimated construction duration at roughly one to two years for the selected segment. Staff told the board they will continue to provide periodic updates and that applicants should expect another update package in September or November.

Context and next steps: staff will monitor permitting paths and funding matches and continue to update cost and schedule estimates as the segment analysis concludes.