Hickman OKs Olsson engineering agreement to design 1-million-gallon reservoir and pump station

City of Hickman City Council · May 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved an engineering agreement with Olsson to design a ground-storage reservoir (roughly 1 million gallons) and a booster pump station to address peak demand and fireflow needs; staff said construction could cost roughly $1.8M–$2M plus land and the project could be bid in about a year.

The Hickman City Council voted to approve a professional‑services agreement with Olsson for preliminary design, geotechnical work and bidding services for a proposed 1‑million‑gallon ground storage reservoir and booster pump station to address growing water demand.

Owen Kllum of Olsson presented the engineering rationale: average daily demand in recent records is “right under 300,000 gallons,” with intermittent spikes to 500,000 gallons and summer peaks over 1 million. Kllum said a ground storage reservoir at the treatment-plant site paired with a booster pump would reduce stress on existing wells, improve pumping efficiency and provide additional capacity for fireflow events. He described a planning horizon of roughly 25 years for sizing and said the firm could deliver bid-ready documents in about a year if land acquisition and scope proceed on schedule.

Estimated construction costs discussed during the presentation were approximately $1.8 million for a ground-storage tank of this size and $200,000–$300,000 for a booster pump station (about $2 million total), excluding land acquisition. Kllum noted that an elevated tower would cost more; site survey and geotechnical borings are required before detailed foundation design.

On funding, staff said water‑utility revenues would cover the engineering agreement and that the city is pursuing an amended $1 million federal appropriation (originally tagged to a wastewater project) with support from Congressman Flood’s office; officials cautioned the federal approval process could take a year. Council members asked about timelines, Buy America/Davis‑Bacon requirements if federal funds are used, and aesthetic/footprint considerations for the tank and pump building.

The council approved the Olsson agreement by motion (moved by Mr. Wagner); the roll-call vote was recorded as unanimous. Council members clarified construction‑phase services would require a separate authorization if council wanted Olsson to remain on during construction.