Kenosha water board approves $442,980 water‑main contract, accepts infrastructure and records easement
Summary
At its April 14 meeting the Board of Water Commissioners approved minutes and disbursements, awarded a $442,980 contract for water‑main relay work, approved a revised quitclaim deed, accepted infrastructure for the Majestic Midwest Innovation Center LLC, and approved a recorded easement with 30th Avenue Yards LLC; commissioners also discussed a 22nd Avenue manhole issue.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Board of Water Commissioners on April 14 approved a series of routine and project-related items, including a $442,980 contract to replace water mains, a corrected quitclaim deed for a city parcel, acceptance of newly completed infrastructure for the Majestic Midwest Innovation Center LLC, and a recorded easement with 30th Avenue Yards LLC.
The meeting opened with the clerk taking roll and confirming a quorum. Commissioners moved quickly through routine business, approving the March 24 meeting minutes and the monthly disbursements by voice vote.
Staff introduced Contract 2025-04-W, described in the agenda as “water main relay package number 2,” and said the project is mainly water-related replacements with a small portion of sewer main relay near 35th Avenue and 65th Street. Staff recommended awarding the contract to the lowest bidder in the amount of $442,980. "This is just a contract with the majority being water related replacements," staff said, explaining the work is intended to address deficiencies discovered during investigations and to accommodate related projects. Commissioners moved, seconded and approved the contract by voice vote.
A separate agenda item corrected language in a previously approved quitclaim deed transferring a parcel from the Kenosha Water Utility to the City of Kenosha. Staff said the Wisconsin Department of Revenue requested changing the recording language from referring to the utility to referring to the resulting "city parcel," and characterized the change as a housekeeping correction to final recording language. The board approved the revised quitclaim deed by voice vote. (Transcript contains inconsistent numeric references to the parcel size; the precise square footage was not specified in the record.)
The commission also accepted sanitary sewer collection and water-distribution facilities installed for the Majestic Midwest Innovation Center LLC, after staff reported that the installations met the specifications, passed required testing and documentation, and that a development agreement between the City of Kenosha, the Kenosha Water Utility and Majestic Midwest Innovation Center LLC was in place. "It's met all the specifications and plans," staff said; the board approved acceptance by voice vote.
Staff explained a need to replace prescriptive easements with a recorded sanitary sewer and water easement from 30th Avenue Yards LLC for infrastructure running along the west side of 30th Avenue and an extension of 32nd Avenue. The current landowner had agreed and documents were in order; the board approved recording the easement by voice vote.
During commissioner comments, one commissioner asked staff for an update on construction activity on 22nd Avenue. Staff said a prior water-main break and repair likely undermined a sanitary manhole, causing it to sink and disrupting connections; staff said the recommended remedy is to replace the manhole with a dog-house style manhole and perform full panel pavement replacement to minimize future issues. "We made the necessary repair... our best assessment is that that water main repair... undermined the sanitary manhole," staff said.
The meeting adjourned after a motion and second.
Votes at a glance: - Approval of March 24 minutes: approved by voice vote. - Approval of March 2025 disbursements: approved by voice vote. - Contract 2025-04-W (water main relay package No. 2): awarded to lowest bidder for $442,980; approved by voice vote. - Revised quitclaim deed transferring parcel from Kenosha Water Utility to City of Kenosha: approved by voice vote; square footage unclear in transcript. - Acceptance of sanitary sewer and water supply facilities for Majestic Midwest Innovation Center LLC: approved by voice vote. - Sanitary sewer and water easement between 30th Avenue Yards LLC and Kenosha Water Utility: approved by voice vote.
What’s next: Staff will proceed with contract award and recording actions; staff is also planning replacement of the affected manhole and pavement work on 22nd Avenue per the board discussion.