BPW approves engineering services for Carlton Pump Station third pump; requests CIP repurposing

Board of Public Works Commission · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Zeeland BPW approved $92,137.50 in professional services to design and supervise addition of a third pump at Carlton Pump Station and requested repurposing two FY2026 CIP items to fund the engineering work; installation will be included in FY2027 CIP.

The Zeeland Board of Public Works approved Nov. 11 an engineering services contract and direction to repurpose FY2026 CIP funds to advance a third pump addition at the Carlton Pump Station.

Water Operations Manager Postma said increased demand in the high-pressure district requires a third pump to provide redundancy and allow the system to operate using best practices when maximum daily flows approach 90% of firm capacity. Staff recommended awarding engineering, design, bidding and construction supervision to Moore & Bruggink Consulting Engineers for $92,137.50. Because the capital expenditure was not anticipated in the FY2026 budget, staff proposed repurposing two non-performed FY2026 CIP projects — a SCADA system replacement ($150,000) and paving for the 80th St. Tank parking area ($50,000) — to cover the engineering/design work now; the installation and construction portion will be included in the FY2027 CIP.

The Board approved the professional services award and the staff approach; minutes record the motion as carried with "all voting aye." Staff noted the installation cost will be budgeted in FY2027.