Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure And Utilities topic

No spam. Unsubscribe anytime.

Florence approves emergency pump‑station repair and advances Hwy. 49 sewer work

Mayor and Board of Aldermen of the City of Florence, Mississippi · July 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Florence board approved $24,107.93 for an emergency repair to the Dogwood Hills Pump Station, authorized purchase of a 4" Inserta Valve for $6,792, approved Pay Request #7 ($12,900.20) to Hemphill Construction and authorized execution of a contract with Thornton Construction for Phase III of the Hwy. 49 sewer additions.

The Florence mayor and board on July 1 approved emergency repairs and contract actions intended to protect sewer infrastructure and advance the Hwy. 49 Eagle Post Road sanitary sewer additions.

City Engineer Tim Parker told the board that repairs to the Dogwood Hills Pump Station were declared an emergency to prevent potential raw sewage leakage. The board approved payment of $24,107.93 to Maintenance Systems, Inc. (invoice M25017‑C‑01‑Final) to cover the repair.

Parker also recommended purchasing a 4‑inch Inserta Valve (Hydra Stop) for distribution system work; the board approved the low quote from Eagle Pipe and Supply for $6,792.00 over Consolidated Pipe & Supply’s $7,200.00.

The board approved Pay Request #7 for Hemphill Construction Company, Inc., for the Hwy. 49 Eagle Post Road sanitary sewer additions Phase II in the amount of $12,900.20; that vote was recorded with Alderman Mason Herrin not participating. The board also authorized and directed Mayor Gunn to execute a contract with Thornton Construction Company, Inc. for the Hwy. 49 Eagle Post Road sanitary sewer additions Phase III project, contingent on the city attorney’s review and approval of contract documents.

Those actions were presented as necessary to protect public health and to continue the sewer additions project; the board recorded motions and roll call votes where specified in the minutes.