The committee approved moving forward with a $233,035 base contract to create a 10-year pavement preservation plan (ICE) and discussed widening roadway striping to 6 inches on primary routes to improve safety, citing FHWA findings.
Get email alerts on the Pavement Management topic
No spam. Unsubscribe anytime.
County engineers told the committee they selected ICE to prepare a 10-year pavement preservation plan and will pursue intergovernmental agreements so municipalities share the cost. "Included in that fee proposal was a base amount of $233,035 to collect the county roads and do a 10 year pavement preservation plan," Brian Bauer said.
Bauer said ICE also proposed an alternate $63,900 inventory to document signs, raised pavement markings and striping quality; that alternate would bring the full contract to $322,995, with municipalities picking up their shares and the county CTC committing to the base $233,035.
Committee members then discussed striping width as a low-cost safety measure. Members cited studies showing wider striping increases visibility and improves safety on higher-speed, primary corridors. "When we do the resurfacing, if it's a primary road or something more high volume, higher speeds, doing 6 inches," Bauer said; other members cited FHWA work supporting wider striping.
Bauer said the plan is to bring IGAs to council in August and aim for a notice to proceed in mid-September if committee and council approvals follow the schedule.
Next steps: staff will present IGAs and the contract to the PFC in August and then to full council; municipalities will be asked to confirm their contributions.