Mono County jail project 40% complete by schedule; $6.5 million in eligible expenses submitted
Summary
County engineer reported the Mono County jail project is about 40% complete by time and has submitted roughly $6.5 million in eligible expenses to the BSCC; officials said they remain on schedule for summer 2027 completion despite invoice and winter-lull timing.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
County engineer Caitlin Dodd updated the Board of Supervisors on June 2 on the Mono County jail construction project, reporting progress on the schedule, finances, and procurement of fixtures and equipment.
Dodd said the county has submitted an invoice to the Board of State and Community Corrections that documents about $6.5 million in eligible expenses to date. By the contractor’s schedule the project is about 40% complete by calendar time; Dodd estimated roughly 25% of field work and materials are complete and said some invoices (for May) were still pending, explaining a temporary lag tied to winter slow-down and billing cycles.
The county remains on track for a projected summer 2027 completion, Dodd said; change orders have been split to expedite electrical work that needed to occur before concrete placement, and one change order that deletes a climbing-mesh item is expected to produce an overall credit of roughly $10,000.
On-site work has included installation of the underslab gravel and vapor barrier and completion of a masonry mock-up wall for quality inspection. Procurement of FF&E (fixtures, furnishings, equipment) is underway; IT and radio compatibility review is ongoing to ensure future dispatch compatibility.
Community engagement and operations: Dodd and supervisors summarized a recent community meeting; attendees asked about construction hours, traffic impacts, and how transit and bus stops will work for people released from custody. Dodd said site circulation is designed as a loop to allow efficient vehicle movement and that the county is coordinating with transit providers, the sheriff’s office, probation and other partners on release accommodations.
Why it matters: The jail is a major capital project for Mono County with state grant funding and local match obligations. Ongoing oversight, pacing of invoices, and coordination on operations and community impacts were the primary topics of supervisor questions.
Next steps: The project team expects to prepare the next quarterly invoice at the end of the month, continue staggered slab pours and wall construction, finalize FF&E procurement, and maintain monthly updates to the board.
Ending: The board accepted the update and supervisors noted plans to follow up with ad hoc meetings for operational details as construction progresses.