Cheltenham staff aim to post La Mott community center bids by July 1 amid residents' questions
Summary
At the June 17 meeting officials said bid documents for the La Mott community center renovation should be posted in early July, with bids due end of July and contractor selection in August; residents pressed for clarity on a referenced $3.8 million in federal funds and for prompt action to avoid further delay.
Get email alerts on the La Mott Renovation topic
No spam. Unsubscribe anytime.
Township officials told the Board of Commissioners on June 17 they expect to finalize and post bid documents for the La Mott community center renovation on OpenGov by July 1, with bids returned by the end of July and contractor selection slated for August.
Commissioner Chirico and Manager Elliott said the township’s engineer is finalizing its portion of the bid package and Re:Vision (the project architect/consultant referenced in committee communications) has indicated the schedule would allow a bid opening in late July and a selection in August, enabling a ceremonial groundbreaking on La Mott Day if the timeline holds. Manager Elliott confirmed a state BHAR application has been submitted and said, to the board’s understanding, the federal funding for the project remains available.
During citizens forum, Gerry Brown of La Mott Citizens United pressed for details: "When are the contractors being selected and when will they start to evaluate the conditions in the building?" Brown also asked specifically about "the status of the $3.8 million given the delays." Manager Elliott replied that bids are expected to be posted in early July, that bids would be evaluated after submission, and that the federal funds referenced remain allocated to the project. Staff committed to follow up with a more detailed timeline and to coordinate a site pre-bid meeting once the OpenGov posting is live.
Residents and commissioners urged urgency. Commissioner Chirico said the board does not want bidding delayed further and encouraged staff to bring in any necessary resources to meet the July goal. Re:Vision emailed staff that bids could be returned by the end of July if posted July 1.
What’s next: staff will post the La Mott bid documents to OpenGov, schedule any pre-bid meetings, and provide updates at committee meetings (public works and building & zoning meetings were suggested for July 1). Funding and contract award timing will depend on bid submissions and standard procurement review.