Board authorizes $229,855 contract amendment for BKV construction‑phase services on Wildwood Plaza renovation
Summary
The Board approved Amendment No. 1 to BKV Group's agreement, adding $229,855 for construction‑phase services to support the Wildwood Plaza renovation. The presenter described the change in delivery method to include a construction manager and provided budget snapshots including a construction manager GMP around $10 million and a current committed total near $10.7‑11.6 million depending on accounting.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Board of Public Works on June 16 approved an amendment adding construction‑phase services from architect BKV Group for the Wildwood Plaza building renovation project intended to house the police department.
A presenter identified in the packet as Josh Marwitz explained that the council previously selected BKV Group of Minneapolis for architectural design and that the project delivery method later changed to include a construction manager. "BKV's construction phase scope of services includes reviewing submittals and shop drawings, responding to contractor questions, conducting regular site visits to observe progress and quality, assisting in evaluating change orders and pay applications, and maintaining alignment between the construction work, the contract documents, the budget, and the project schedule," the presenter said.
The amendment would add a construction‑phase services fee of $229,855 for BKV Group. Project budget figures presented in the packet and read into the record included a construction manager guaranteed maximum price (GMP) reported at roughly $10 million, committed architect/design contracts and related costs that bring the current committed total to about $10,725,000, and grants that the presenter said bring available budget to $10,800,000; another speaker characterized the rough price point as "11.6 million." The presenter said the amendment clarifies roles and avoids duplication between the city, architect and construction manager.
A board member moved to approve amendment number one to the city's agreement with BKV Group for construction phase services in the amount of $229,855; the motion was seconded and carried on voice vote.
The Board authorized execution of the amendment; the transcript records no roll‑call tally.