Eagle approves plans and awards contract for 2026 Mill & Overlay on Eagle Drive
Summary
The board approved Snyder & Associates’ construction plans and Opinion of Probable Cost for a $158,300 mill-and-overlay project on Eagle Drive and awarded the construction contract to Cather & Sons Construction for $127,872.50.
Get email alerts on the Streets Infrastructure topic
No spam. Unsubscribe anytime.
The Village of Eagle Board approved plans and a cost estimate for the 2026 Mill & Overlay Improvements Project on Eagle Drive and awarded the contract at its April 7 meeting.
Trustee Dan Meier moved and Trustee John Surman seconded approval of construction plans and an Opinion of Probable Cost submitted by Snyder & Associates listing $158,300 as the probable cost. The minutes record the vote as 'Ayes — 5; motion carried.' (Attendance earlier in the minutes lists four trustees present; see audit for the recorded-tally discrepancy.)
Separately, the board voted to award the 2026 Mill & Overlay Improvements contract to Cather & Sons Construction for $127,872.50. That motion (Surman/Meier) is recorded as carried with Voting: Ayes — 4.
At the same meeting the board approved staff training attendance for Curtis Klabenes to attend a wastewater continuing education course in Auburn on April 22, 2026. The minutes list routine approvals for meeting minutes and claims as presented; approved claims totaled $90,997.11 and approved park claims totaled $718.99.
No change orders, construction start date, or contract duration were recorded in the minutes; the item in the record covers plan approval and contract award only.