Change order of $28,310 approved for Fairview 69kV breaker testing and commissioning

Board of Public Works Commission · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

BPW approved Kent Power’s change order, including Shermco subcontracted testing services, for $28,310 to complete high-voltage commissioning on the Fairview Substation breaker replacement project; the total project cost is now about $460,199, below the $500,000 budget.

The Zeeland Board of Public Works approved a $28,310 change order from Kent Power to cover independent high-voltage testing and commissioning services for the Fairview Substation 69kV breaker replacement project.

Staff explained the change order resulted from a miscommunication about the scope of testing included in the construction contract and said NERC best practices and industry norms require independent third-party testing of high-voltage equipment prior to energization. Kent Power secured Shermco Industries to perform the required testing and included Shermco costs, specialized commissioning equipment and Kent Power labor in Change Order COR001-REV001.

Board materials indicate these services were procured and completed to maintain the project schedule. Approving the change order brings the estimated total project cost to approximately $460,199, which staff said remains under the approved $500,000 project budget. The Board approved the change order on a motion by Commissioner Cooney, seconded by Commissioner Walters; the motion carried unanimously.

Staff said no additional project expenses are anticipated and that the equipment was placed into service following completion of the testing and commissioning work.