Board reviews berm-removal, gravel estimates and Station Road ditch concerns
Summary
The Select Board received updates on berm removal and cemetery/road repairs with cost estimates, heard a Station Road ditch complaint affecting hay fields, and noted pending bids for gravel repairs and paving.
Get email alerts on the Transportation Roads topic
No spam. Unsubscribe anytime.
During the Aug. 19 meeting the board heard several road-related updates. The Road Commissioner reported contacting two paving companies (one provided an estimate; the other requested a map of roads), completed roadside mowing, and completed berm work at Williams Cemetery. Plans to remove berms will wait for dry weather. Gravel-repair estimates are expected at the next meeting.
A resident identified as Jim P. asked the board to address ditch work on Station Road, saying water is running across the road into his hay fields and that only one culvert is functioning. The Road Commissioner said trees are growing in the ditch and that prior cleaning had been done a couple of years ago.
The minutes record suggested repair approaches and cost estimates: leave roots and add 6–8 inches of gravel (noted as 8 inches = 36 yards at approximately $1,500), and for Middle Road skim grass to gravel and add three loads of gravel (cost cited $1,500). The board also queried the status of a $50,000 grant that could relate to road work; no final determination was provided during the meeting.
Actions on paving and larger repair bids were deferred to future meetings; the board asked staff to obtain bids and return with numbers for review.