Council approves WRF pay request ($2.635M) and several airport payments; wastewater project ~38% complete
Summary
Council approved a $2.635 million pay request to PKG Contracting for wastewater facility improvements and authorized three airport invoices and a snow removal equipment building design invoice; staff reported the WRF project is about 38% complete and the airport terminal construction is progressing.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The council approved multiple infrastructure payments and heard project updates. Amanda, the project lead on the wastewater treatment facility (WRF) improvement project, reported the work is approximately 38% complete and includes demolition, pre‑treatment bypass pumping, construction of new pre‑treatment channels and UV disinfection work; contractors have poured final slabs and are nearing the final clarifier pours. Staff recommended approval of a $2.635 million pay request to PKG Contracting; the council approved the payment after a roll call, with an abstention noted by one member on specific vendors.
Transportation Director Rich reviewed three airport invoices related to the terminal expansion: two Helms invoices ($8,119.35 and $7,073.24) for resident engineering and construction administration, and Quest Construction pay estimate #4 for $92,727.08. He summarized project funding from Senate Bill 144 ($1.2 million), federal AIP/IIJA grants (roughly $864,600 total cited) and a projected local share of about $60,000. Rich said concrete floors were poured and the new baggage make‑up room framing was erected, signaling steady progress.
Rich also described invoice #6 for design and administration of the snow removal equipment (SRE) building expansion ($11,200.43), a project that is roughly 15% complete and funded by a mix of federal (95%), city (2.5%) and state (2.5%) dollars; council approved that payment as well.
Council thanked staff for project oversight and noted ongoing monitoring of construction schedules and weather impacts to the WRF site.