Council approves design amendment for hypochlorite-generation replacement at Stones River plant; construction estimated at about $2.2 million

Murfreesboro City Council · June 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $270,587 design task-order amendment to replace an aging hypochlorite-generation system at the Stones River Water Treatment Plant with a MicroClaw system; staff estimated construction costs at roughly $2.2 million.

City staff described amendment two to the Stones River Water Treatment Plant project, recommending design of a MicroClaw hypochlorite-generation system to replace an aging Claw Tech unit. Staff said the original system’s parts have become obsolete and that the MicroClaw design (amendment two) is estimated at $270,587 for design work; estimated construction costs are about $2.2 million.

Staff explained the current system was 17 years old and that the proposed replacement would provide multiple cell redundancy so that a single cell failure would not take the entire rack offline. Council moved and approved the task order amendment by roll call.

The project will proceed to design; construction will follow according to standard procurement and budget processes and will be scheduled and funded per department capital plans.