Brewer awards Pier Park trails design contract, uses Maine Trails grant funding

Brewer City Council · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City of Brewer awarded a $52,700 engineering and design contract for Pier Park trails to Acorn Engineering on May 12, to be funded by a $250,000 Maine Trails Program grant; Council authorized up to $58,000 including contingency and made the purchase contingent on a fully executed state project agreement.

The Brewer City Council voted to award a contract for engineering and design services for the Pier Park Trails Project to Acorn Engineering, accepting the firm’s $52,700 proposal and authorizing appropriation of up to $58,000 including a 10% contingency, with work to be funded by a $250,000 Maine Trails Program grant.

The Council’s order (2026-A091) follows the City’s February 20, 2026 request for proposals and an evaluation of candidates on project understanding, experience, schedule and fee; the staff report listed competing proposals and identified Acorn Engineering as the lowest-priced qualified bidder. The Council made the contract contingent on the City’s receipt of a fully executed Project Agreement with the Maine Department of Agriculture, Conservation and Forestry.

The order authorizes the Brewer City Manager to execute a professional services agreement and charges the appropriation to the Maine Trails Program Pier Park Grant expense account. The Pier Park project will support planning, permitting and design of a multi-use trail system and related waterfront improvements along the Penobscot River.

Councilors approved the order on the consent calendar by unanimous vote at the May 12 meeting.

Next steps: execution of the Project Agreement with the State will permit the City Manager to finalize the contract and begin design work funded by the grant.