Salem council authorizes grant application, commits $250,000 toward South Lincoln rail overpass
Summary
Salem City Council unanimously approved a resolution Feb. 3 to apply for a federal-state rail partnership grant and commit $250,000 as the city's portion of a $500,000 local match for a proposed South Lincoln Avenue overpass; total project cost is estimated at $27 million.
Get email alerts on the Rail Overpass topic
No spam. Unsubscribe anytime.
Salem City Council on Feb. 3 authorized the city to apply for a federal-state intercity passenger rail partnership grant and committed $250,000 as the city's share of a $500,000 local match for a proposed South Lincoln Avenue rail overpass.
Safety service director Mr. Capsello told the council the overall project is currently estimated at $27 million and that Columbombiana County would provide the other $250,000 of the local match. "Total project right now is estimated to be $27 million," he said, adding that Gov. DeWine has committed more than $5 million and that federal funding would account for roughly $21 million if the application succeeds.
Council members discussed site selection and safety concerns. Council Member Mr. Ty noted the crossing "has been identified as a dangerous crossing by the state and railroad transportation department" because of the high number of trains and vehicle traffic. Speakers said the overpass would improve emergency response times, reduce idling and fuel use, and could improve property values near the crossing.
Council moved to suspend rules and read the resolution for first, second and third readings with an emergency clause; the roll-call vote was recorded as "yes" by all members present. Mr. Capsello said the application deadline was imminent and that, if everything proceeded without delay, construction could begin as late as January 2032.
The resolution directs staff to submit the application and confirms the city's local commitment; the project remains contingent on approvals and grant awards by state and federal agencies.